At the site of the Slavyanskaya compressor station, the basic construction and installation works of stage 2.1 has been completed. The transfer of systems to commissioning and the elimination of corrections are still underway.

The Slavyanskaya CS is located in the Kingisepp district of the Leningrad Region and is being constructed as part of the project for “Development of the UGSS gas transmission capacity in the North-West region, section Gryazovets – Slavyanskaya compressor station”.

At the Slavyanskaya CS, 11 gas pumping units (GPA-32 Ladoga) with a total capacity of 352 MW are to be installed. The installation of six gas pumping units included in stage 2.1, as well as gas air cooling unit and gas treatment plants has been completed. The technological pipeline and equipment are being dried; installation of buildings and structures included in stage 1 of construction has been completed: Service/Operation Building, office and living quarters, pump station, checkpoint, warehouses, parking garage, fire station.

Landscaping work is being carried out. The construction of on-site, off-site networks and access roads has been completed; fencing of the territory of the compressor station is in the final stage.

About 1400 employees of Lengazspetsstroy and Neftegazkomplektmontazh companies work on the site. Gas supply to the Slavyanskaya compressor station is scheduled for April this year.